The U.S. Embassy in Bujumbura, Burundi, has a requirement to replace the faulty Programmable Logic Controller (PLC) of its Domestic Water Treatment Plant (DWTP) and integrate BACnet communication to enable connectivity with the Building Automation System (BAS). This upgrade will allow the Facilities Team to monitor water levels, production, and distribution to Embassy buildings in real time, in accordance with the attached Statement of Work (SOW).
The existing PLC, an Allen-Bradley MicroLogix 1200, has experienced a fatal internal failure and must be replaced.
All interested vendors are requested to submit their best and final quotation no later than July 18, 2026, at 10:00 a.m. Bujumbura time, for the following requirement:
Domestic Water Treatment Plant (DWTP) System – PLC Supply, Installation, Programming, Integration, Testing, and Commissioning Services
Vendors must provide a detailed and itemized price quotation. Lump-sum or incomplete pricing that does not clearly identify individual components and services may not be considered during the evaluation process. Each line item should include sufficient detail for technical and price analysis.
The quotation should, at a minimum, include the following categories:
1. Staff Services
Technical personnel
Labor costs
Travel expenses
Accommodation and per diem (if applicable)
Engineering and programming services
Testing and commissioning services
2. Materials and Equipment
PLC hardware and accessories
BACnet communication modules and interfaces
Software licenses (if applicable)
Control panels, cables, connectors, and related components
Any additional equipment required for a complete installation
3. Installation and Commissioning
Removal of existing PLC
Installation of new PLC and associated equipment
Programming and system configuration
BAS integration and BACnet communication setup
Functional testing
System commissioning
Operator training and documentation
Please ensure that all proposed equipment and services comply with the requirements specified in the attached Statement of Work.
Amendment 1: See all attached.The new offer due date is September 5, 2026
The contractor must replace the faulty Main PLC (Allen-Bradley MicroLogix 1200) and upgrade the BAS Integration module to BACnet to pool all points from the Potable and Pump system, including the main PLC, Triplex pump PLC, and Booster pump PLC. Work includes providing a new unlocked PLC and HMIs, all hardware and software, upgrading input/output cards, installing BACnet converter and ethernet switch, performing re-wiring and labeling, and ensuring the new PLC footprint fits the existing cabinet or adding a new cabinet. The contractor must also provide a minimum of eight hours of hands-on training to Facility personnel covering software, system operations, alarm management, and basic troubleshooting.
"US""20520""WASHINGTON""DC""USA""DEPARTMENT OF STATE, 2201 C ST NW""Amendment No1 Questions tobe posted.pdf"147026"file"".pdf""1""2026-07-31T10:07:22.308+00:00""d05760e349444fa095dc84d860728743""public""0""public""c27b6b381dea43cd862926202e7769ee""0"3"0""SOW - NEC DWTP FAULTY PLC REPLACEMENT_2026 - V3.pdf"5735140"file"".pdf""1""2026-07-31T10:07:22.308+00:00""ff040ecc7ff845aaa8850e01ed5e196e""public""0""public""87ea5002f48840fa834eef79b1d9f637""0"2"0""19BY7026Q0010_StatementOfWork.pdf"402393"file"".pdf""1""2026-06-22T07:38:29.033+00:00""120e35a0d2194f47a059f594231795f8""public""0""public""e5fa3ce076e144f2aa2f528cebd57d0e""0"1"0"Source: SAM.gov (notice f75643b110264313b8fa69feae99eeed), retrieved via the SAM.gov Get Opportunities API. View the official posting , always confirm requirements and deadlines with the issuing agency.