PEDESTRIAN IMPROVEMENTS (SIDEWALKS)
CITY STREET (EAST BROADWAY): FROM THE INTERSECTION OF LAKE DRIVE,
EXTEND WEST IN THE TOWN OF PRUE.
PROJECT LENGTH = 0.092 MILES
The work includes 222 CY of unclassified excavation, 1 LSUM of type A-salvaged topsoil, 35 LF of temporary silt dike, 1,131 SY of solid slab sodding, 3 CY of aggregate base type A, 7 CY of class C concrete, 222 SY of 4" concrete sidewalk, 14 SY of 6" concrete driveway, 52 SF of tactile warning device-new, 32 LF of 12" corrugated polypropylene pipe, 16 LF of 15" corrugated polypropylene pipe, 31 CY of standard bedding material class C, removal and resetting of existing signs, sheet aluminum signs, square tube posts, traffic stripe, construction signs, rectangular rapid flashing beacons (add alternates), construction staking level II, and mobilization.
We post new concrete opportunities in Oklahoma as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Oklahoma work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Oklahoma Department of Transportation (solicitation 260276), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.