We post new general contractors opportunities in Utah as agencies publish them. Get them in one email — free, and unsubscribe whenever.
When sending email correspondance for this project to SSgt Ruano Gutierrez AND Hideo Mera please include the notice ID and project name in the subject line of the email.
5 June: Updated to solicitation to include photos from site & extend due date.
9 June: Updated to include updated drawnings for the mezzanine site & extended due date to 25 June.
22 June: Updated to extend due to to 10 July & Questions period to 2 July to accomdate new questions.
7 July 2026: Updated to extend due date to 22 July 2026; Questions will now be accepted until 17 July. Update also includes date for new site visit on 14 July 2026 at 0900. RSVP NLT 1500 on 10 July. Further details will be provided upon RSVP. Update also includes question responses and updated SOW for the project.
17 July 2026: Extending due date to 3 August to allow time to answer RFIs received after 14 July site visit. Additional questions will not be accepted at this time.
05 August 2026: The most up to date questions and responses have been uploaded. New due date to submit quotes/updated quotes will be 18 August 2025 at 1500 Mountain Time.
The contractor shall provide all labor, materials, and equipment to design and construct a 30' x 40' mezzanine in Building 238, South Center, including a fully enclosed space with an office, break room, and multi-purpose area. Work includes structural steel, decking, stairs, enclosure framing, interior finishes, electrical, data, lighting, and coordination for fire alarm/suppression systems. The design must prioritize a maximum of nine support columns bolted to the existing slab, with a minimum 11'0" clear height below. The contractor is responsible for work area cleanup and debris removal.
"84056-5805""HILL AFB""UT""USA""CP 801 586 8612""6038 ASPEN AVENUE BLDG 1289""15340 - Additional Contractor Questions n Answers.docx"20204"file"".docx""1""2026-08-05T21:38:24.215+00:00""7dd01b113a1d4e728547defe19b62af1""public""0""public""281b90f860b8476fa41950b0fcf12450""0"11"0""15340 - 238 Mezzanine and Modular Office SOW - Updated.pdf"142301"file"".pdf""1""2026-07-07T20:47:30.495+00:00""2681e21f32114da6ac8d72576b001b2d""public""0""public""f54820d28e204b018726fe125fb6bd36""0"10"0""15340 - Contractor Questions n Answers.pdf"102918"file"".pdf""1""2026-07-07T20:47:30.495+00:00""2ee1e8b0a3b948dca717c560218e7b09""public""0""public""627516321e75486dac174d013053ed3f""0"9"0""15340 - Updated Drawings.jpeg"629895"file"".jpeg""1""2026-06-09T15:40:31.574+00:00""361cc0171d24473183b03a1a8e0dd651""public""0""public""36b98889774b46ae80cf038e7cfb52e4""0"8"0""IMG_0608.jpg"6442383"file"".jpg""1""2026-06-05T20:28:39.662+00:00""602e8df55c414d86bdc4409fc6f85349""public""0""public""2a0497a8fa2e4581a043ddef73fe919c""0"7"0""IMG_0607 2.jpg"5565813"file"".jpg""1""2026-06-05T20:28:39.662+00:00""9cf70e32545e42dda680b026f1d413cb""public""0""public""2f6e3f6b662c4f40b8a9a70ab32e539f""0"6"0""IMG_0606.jpg"5405748"file"".jpg""1""2026-06-05T20:28:39.662+00:00""cd7fd35938e94d99a8cbecd48860640b""public""0""public""3447a56a543c4b34a8b2d62652cbf537""0"5"0""15340 - 238 Mezzanine Modular Office Combo.pdf"289932"file"".pdf""1""2026-06-01T19:15:25.744+00:00""9838687cb8d54b67ad2319ee6a2bdcee""public""0""public""0c91f74667f14410b7c3a1ec48d6f174""0"4"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
Source: SAM.gov (notice 145c0a7a8de241b9919e0684ed73e37c), retrieved via the SAM.gov Get Opportunities API. View the official posting , always confirm requirements and deadlines with the issuing agency.