This project is the asphalt milling and patching, full-width paving, including minor drainage improvements and guiderail upgrades Along SR 268 and other miscellaneous construction, as indicated on the approved drawings included in the bid package for STATE ROUTE 268, SECTION 103, in Armstrong COUNTY Sugarcreek and East Franklin TOWNSHIP from approximately from Stoney Batter Rd at segment 0110 offset 2806 to approximately south to 0.31 miles south of Boltz Rd at segment 0280 offset 2712.
Additional Information: This is an ECMS project. All Addenda will be electronically posted. The location of the public bid opening is the Commonwealth Keystone Building, 7th Floor, Contract Awards Room, 400 North Street, Harrisburg. Allow sufficient time before the bid opening to obtain a visitor pass on the 5th Floor and to be escorted to the 7th Floor Contract Awards Room.
The work includes asphalt milling and patching, full-width paving, minor drainage improvements, and guiderail upgrades along SR 268 from Stoney Batter Rd at segment 0110 offset 2806 to approximately 0.31 miles south of Boltz Rd at segment 0280 offset 2712, in Sugarcreek and East Franklin Township, Armstrong County, Pennsylvania, as indicated on the approved drawings included in the bid package.
We post new asphalt opportunities in Pennsylvania as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Pennsylvania work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Pennsylvania Department of Transportation (PennDOT) (solicitation PENNDOT_99923_1), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.