The Contractor must furnish the labor and materials necessary to install approximately ±271 LF of 8" SDR 26 PVC gravity sewer, ±55 LF of 2" SCH 80 PVC force main, ±60 LF of 2" PE Force Main, and a packaged duplex lift station with 2 HP pumps. Installation shall include all work shown in the construction plans, including valves, manholes, and other appurtenances.
Ellijay-Gilmer County Water & Sewerage Authority C & S Project No. E2100.015
South Main Street Lift Station September 2026
00100-1
PROPOSAL ADVERTISEMENT
PART 1. GENERAL
1.1 SEALED PROPOSALS
Sealed Proposals for construction of South Main Street Lift Station will be received until
Thursday, November 12, 2026 at 2:00 PM. Proposals must be submitted electronically at
QuestCDN.com. No paper submissions will be allowed. Any proposal received after said
time and date will not be considered by the Owner. No Proposal may be withdrawn after the
closing time for the receipt of Proposals for a period of sixty (60) days.
1.2 SCOPE OF WORK
Under this project, the Contractor must furnish the labor and materials necessary to install
approximately ±271 LF of 8" SDR 26 PVC gravity sewer, ±55 LF of 2" SCH 80 PVC force
main, ±60 LF of 2" PE Force Main, and a packaged duplex lift station with 2 HP pumps.
Installation shall include all work shown in the construction plans, including valves,
manholes, and other appurtenances.
Time allotted for completion of work is 120 consecutive calendar days. All Work shall be
completed in accordance with the plans and specifications. The Work will be awarded in one
(1) Contract.
1.3 PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS
Complete digital specifications and contract documents are available at
www.QuestCDN.com. You may view the digital documents for free by entering the Quest
project number 10393529 on the website’s project search page. The fee to download the
digital documents is $150 payable through the website. There will be a $50 fee to submit the
Proposal online. Proposals must be submitted electronically at QuestCDN.com.
Under this project the Contractor must furnish labor and materials to install approximately ±271 LF of 8-inch SDR 26 PVC gravity sewer, ±55 LF of 2-inch SCH 80 PVC force main, ±60 LF of 2-inch PE force main, and a packaged duplex lift station with 2 HP pumps, including valves, manholes and other appurtenances as shown in the construction plans, with all work completed in accordance with the plans and specifications within 120 consecutive calendar days under one contract.
We post new plumbing opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-66199-NONST-2027-000000003), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.