REQUEST FOR PROPOSALS
Underground Fiber Optic Drop Installation Services
Burke County, Georgia
RFP No.: RFP-2026-BB-001
RFP Issue Date: July 31, 2026
Proposal Due Date: September 2, 2026, 12:00 PM Eastern Standard Time
Questions Due: August 26, 2026, 2:00 PM Eastern Standard Time
Addendum Posted on Website: Friday, August 28, 2026, 5:00 PM Eastern Standard Time
Issued by:
Burke County Board of Commissioners
Burke County Manager's Office
PO Box 89 | 602 N. Liberty Street
Waynesboro, GA 30830
Contact: Adam Flakes | a.flakes@burkecounty-ga.gov
This document constitutes a Request for Proposals and does not commit Burke County to
award a contract or to pay any costs incurred in the preparation of proposals.
P a g e 2 | 32
TABLE OF CONTENTS
SECTION 1: INTRODUCTION AND BACKGROUND .................................................................................. 4
1.1 Purpose and Background ................................................................................................................... 4
1.2 Federal Compliance ............................................................................................................................ 4
1.3 Award Authority .................................................................................................................................. 4
SECTION 2: SCOPE OF WORK — STANDARD DROP INSTALLATION .................................................. 4
BEHAVIOR EXPECTATIONS .............................................................................................................. 5
BACKGROUND CHECKS AND DRUG TESTING ...............................................................................
The Contractor shall perform underground fiber optic drop installations including burying drop fiber (plowing, trenching, or boring), installing riser guards, valve boxes for slack storage, and Fiber Optic Termination Boxes on the exterior of premises. The Contractor must integrate with the ISP's work order management system, coordinate with Georgia 811 for utility locates, and provide photographic and GPS documentation. Work includes residential and commercial connections, with the County providing all materials and the Contractor providing labor and site restoration.
Source: Georgia Procurement Registry (solicitation PE-61700-NONST-2026-000000077), retrieved via the Georgia Procurement Registry (DOAS). View the official posting , always confirm requirements and deadlines with the issuing agency.