Fund Construction modifications to the M/V Tazlina to incorporate sleeping quarters for up to 24 persons, add 8 single person staterooms on the Bridge Deck, and 8 two]person staterooms on
the Upper Deck. Additional work includes the installation of a Galley; Scullery; Mess Spaces on the Upper Deck; modify the EGR Fuel System; a new Fan Room on the Bridge Deck; modifications to the existing
passenger dining area; extensions to the existing port stair tower to provide Crew access to the Bridge Deck; construct storage and office on the Passenger Deck; modify Passenger Deck Childrens Play Area;
perform coatings and protection upgrades; and perform State Funded Annual Overhaul Work and upgrades. Following removals required for construction, the vessel shall be modified by addition of the new
structure, piping, electrical, toilet/shower modules, lighting fixtures, ceiling, wall insulation and linings, deck coverings, furniture, galley equipment and fixtures necessary to accommodate the revised vessel
arrangement. All ancillary work required to complete the modifications shall be included in this project. The department requests authorization to use funds for in-state and out-of-state travel to manage construction at a shipyard.
Contract #: SFTAG00624
Federal Project #: 9500165
IRIS Program #: SFTAG00624
On the Job Trainees/Apprentices (item 645): None
Engineer's Estimate Range: Between $30,000,000 and $40,000,000
Bid Opening: 10/27/2026 (before 2:00 PM local time)
Advertise Date: 10/8/2026
Region: Southcoast Region
Community: Statewide
Fund Construction modifications to the M/V Tazlina to incorporate sleeping quarters for up to 24 persons, add 8 single person staterooms on the Bridge Deck, and 8 two-person staterooms on the Upper Deck. Additional work includes the installation of a Galley; Scullery; Mess Spaces on the Upper Deck; modify the EGR Fuel System; a new Fan Room on the Bridge Deck; modifications to the existing passenger dining area; extensions to the existing port stair tower to provide Crew access to the Bridge Deck; construct storage and office on the Passenger Deck; modify Passenger Deck Childrens Play Area; perform coatings and protection upgrades; and perform State Funded Annual Overhaul Work and upgrades. Following removals required for construction, the vessel shall be modified by addition of the new structure, piping, electrical, toilet/shower modules, lighting fixtures, ceiling, wall insulation and linings, deck coverings, furniture, galley equipment and fixtures necessary to accommodate the revised vessel arrangement. All ancillary work required to complete the modifications shall be included in this project.
We post new architecture and design opportunities in Alaska as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Alaska work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Alaska Department of Transportation & Public Facilities (solicitation SFTAG00624), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.